Executive command center
One active disruption. The most urgent operational condition is shown first; every figure links to the records it came from.
Active S1 disruptionINC-2026-0113
Meridian Stamping ransomware — ERP and EDI unavailable
Meridian Stamping (Tier 1) reported a disruption via supplier notification (vp operations, phone + letter). Services unavailable: Order and release intake (830, 862); ASN generation (856); Outbound shipping labels; Invoice transmission (810). Containment at supplier: in_progress.
Time to first production impact
T−22.4h
Plants at risk
3of 3
Lines at risk
8of 8
Units at risk
3,662in 48h
Estimate from modelled downtime
Revenue at risk
$130.2M
Estimate, not a booked figure
Customer orders short
1of 40 on exposed lines
246 units · $6.7M
Suppliers requiring action
5
Recovery gates passed
1/11
Exposure cannot be fully determined. Missing information increases—not decreases—decision risk.
- ▲Meridian has not confirmed whether shipment and release data was altered before encryption.
- ▲6 part–line pairs in the traced set have no current inventory record.
- ▲Belmont Die Casting qualification (ALT-2) is 311 days old and unapproved.
- ▲SC Assembly build-ahead bank plan (BCP-3) has never been tested.
Lines at risk, soonest first
| Line | Plant | Program | Hours to impact | Units | Revenue | Status |
|---|---|---|---|---|---|---|
| Line SC-2 (final assembly) | Synthetic SC Assembly | Synthetic X-Program SX-1 | 22.4h | 1,126 | $46.4M | Confirmed |
| Compact Trim | Synthetic Kitchener Assembly | Synthetic X-Program SX-2 | 28.2h | 950 | $26.0M | Confirmed |
| Line SC-3 (chassis) | Synthetic SC Assembly | Synthetic X-Program SX-2 | 28.3h | 1,024 | $28.1M | Confirmed |
| Frame Line | Synthetic Saltillo Assembly | Synthetic Pickup Program | 33.2h | 562 | $29.7M | Confirmed |
| Line SC-1 (body) | Synthetic SC Assembly | Synthetic X-Program SX-1 | 52.3h | 0 | $0k | Possible |
| Van Body Line | Synthetic Kitchener Assembly | Synthetic Commercial Van Program | 59.2h | 0 | $0k | Confirmed |
| Final Trim 2 | Synthetic Saltillo Assembly | Synthetic Pickup Program | 71.5h | 0 | $0k | Confirmed |
| Chassis Sub-assembly | Synthetic Saltillo Assembly | Synthetic Pickup Program | 84.4h | 0 | $0k | Probable |
Confirmed material impactProbable or imminentPossible / evidence gapResponse underwayValidated operationalUnknown / not assessed
Operational exposure score
62.8/ 100 · high
- Production criticality65 × 25% = 16.34 critical of 8 exposed lines across 3 plants
- Time to inventory exhaustion65 × 20% = 13.0First impact in 22.4h
- Supplier concentration40 × 15% = 6.04 of 10 affected parts are single-source
- System and integration dependency100 × 15% = 15.014 systems, 11 critical interfaces, 6 with no manual fallback
- Recovery readiness66 × 10% = 6.61/11 gates passed, 2/3 plans tested, 2/5 alternates qualified
- Financial exposure52 × 10% = 5.2$130.2M revenue at risk over 48h
- Evidence confidence15 × 5% = 0.8Mean path confidence 87%, 1 unresolved part–line pairs
Critical actions and decisions
Overdue or due within 4h (P1)
- Disable Meridian service credentialsT+2h
- Confirm affected part numbers at SC Assembly and SaltilloT+3h
- Validate usable inventory excluding quarantineT+4h
- Activate manual EDI processing (BCP-1)T+4h
Executive decisions required
- Decision: authorise expedited freight premiumCOO · due T+6h · awaiting approval
- Decision: authorise reconnection when gates passCOO · due T+36h · awaiting approval